Multiple Choice
In monitoring project time (schedule) performance, actual performance should be compared to
A) budgets for the current year.
B) top management's targets.
C) project network schedule derived from the WBS / OBS.
D) progress on similar past projects.
E) previous status reports.
Correct Answer:

Verified
Correct Answer:
Verified
Q22: What is a "rubber baseline" and how
Q23: Baseline project budgets are derived from<br>A) the
Q24: The baseline is derived from merging information
Q25: A project manager notices that $5,560 worth
Q26: The schedule variance is the best way
Q28: Schedule variance measures progress in time units.
Q29: Conducting an earned value analysis requires three
Q30: The third step in the project control
Q31: Although it is very difficult to measure,
Q32: A negative CV indicates the project is