Multiple Choice
The start of a task may be moved on a tracking Gantt due to
A) increase in earned value.
B) lack of an updated control chart.
C) a predecessor task starting late.
D) Both an increase in earned value and a lack of an updated control chart.
E) All of these alternatives are correct.
Correct Answer:

Verified
Correct Answer:
Verified