Multiple Choice
Taking action in the four steps for measuring and evaluating project performance can only happen after _________.
A) setting a baseline plan.
B) setting a baseline budget.
C) measuring progress and performance.
D) comparing plan against actual.
E) writing a progress and performance report.
Correct Answer:

Verified
Correct Answer:
Verified