Multiple Choice
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
A) planned value (PV)
B) earned value (EV)
C) schedule variance (SV)
D) cost variance (CV)
E) None of these alternatives is correct.
Correct Answer:

Verified
Correct Answer:
Verified