Multiple Choice
Given an EAC of $10,000 and a BAC of $15,000, the project is expected to be completed _________.
A) over budget
B) under budget
C) over budget but ahead of schedule
D) under budget but behind schedule
E) on budget
Correct Answer:

Verified
Correct Answer:
Verified