Multiple Choice
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
A) Risk Breakdown Structure
B) Work Breakdown Structure
C) Gantt Chart
D) Organization Breakdown Structure
E) Risk Register
Correct Answer:

Verified
Correct Answer:
Verified