Multiple Choice
The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?
A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost more than planned
E) There is not enough information to draw a conclusion
Correct Answer:

Verified
Correct Answer:
Verified