Multiple Choice
The first step in the creation of a Program Evaluation Review Technique (PERT) /Critical Path Method (CPM) chart is to _____.
A) the graphical planning aids to use
B) determine the logical order of project tasks identify
C) determine the status of all tasks
D) identify all the project tasks
Correct Answer:

Verified
Correct Answer:
Verified