-Defines the tasks that can start at the same time
A) Project management
B) Project coordinator
C) Project leader
D) Milestone
E) Constraint
F) Weight
G) Program Evaluation Review Technique (PERT)
H) dependent
I) Concurrent tasks
J) Predecessor tasks
Correct Answer:

Verified
Correct Answer:
Verified