Multiple Choice
Mark, the chief editor of a magazine, needs to create a list of all the in-house writers, designers, and freelancers who will be working on the next issue of the magazine. He also needs to list their activities, their schedules, and their cost per hour. In the context of project management, which of the following should Mark use to create this list?
A) Project crashing
B) Project chartering
C) Standard buffering
D) Fast-tracking
E) Resource loading
Correct Answer:

Verified
Correct Answer:
Verified