Multiple Choice
Vanessa, a student, has to submit two assignments, A and B, on the same day. Each assignment is divided into three tasks. She has to write the first draft, check it for accuracy, and let her friend review it before submission. Each of these tasks takes 5 hours. In order to multitask effectively, Vanessa should:
A) complete the first two tasks of assignment A and start on assignment B while her friend reviews assignment A.
B) complete both assignments simultaneously for her friend to review.
C) complete the first task for each assignment before moving on to the second task and so on.
D) complete assignment B after assignment A has been reviewed.
E) complete assignment A after assignment B has been reviewed.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Crashing non-critical activities will influence project duration.
Q24: Task duration is not necessarily dictated by
Q25: A task's duration is a function of
Q26: Mark, the chief editor of a magazine,
Q27: Pools of like resources from which labor
Q29: Explain the concept of a feeding buffer.
Q30: The safety time added to chains other
Q31: Projects often compete with each other for
Q32: Pools of like resources from which labor
Q33: The following describes which priority rule: With