    The Shortest Time to Complete a Network Is Equal to the Duration
Solved

The Shortest Time to Complete a Network Is Equal to the Duration

Question 98

Question 98

True/False

The shortest time to complete a network is equal to the duration of the longest path through the network.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q93: A situation where two or more activities

Q94: All project-related statistical calculations are performed using

Q95: An event is a series of connected

Q96: The cost to complete an activity is

Q97: Explain why the term critical path has

Q99: Float refers to the amount of time

Q100: Which type of following precedence diagramming convention

Q101: Nessage Mique, a niche fashion boutique, displays

Q102: Milestones in a project consume no resources

Q103: The difference between LFT and EFT is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines