Multiple Choice
Nessage Mique, a niche fashion boutique, displays its production process by using a network of nodes and arrows. The nodes are used to depict the state of completion of various activities and the arrows are used to depict their order of precedence. Which of the following project networks is Nessage Mique using in the given scenario?
A) An event-on-arrow network
B) A time-on-arrow network
C) An activity-on-node network
D) A time-on-node network
E) An activity-on-arrow network
Correct Answer:

Verified
Correct Answer:
Verified
Q96: The cost to complete an activity is
Q97: Explain why the term critical path has
Q98: The shortest time to complete a network
Q99: Float refers to the amount of time
Q100: Which type of following precedence diagramming convention
Q102: Milestones in a project consume no resources
Q103: The difference between LFT and EFT is
Q104: Which type of precedence diagramming convention is
Q105: The start-to-finish linkage is used in situations
Q106: Critical path tasks always have zero slack.