    What Is the Standard Deviation of a Task with Optimistic
Solved

What Is the Standard Deviation of a Task with Optimistic

Question 2

Question 2

Multiple Choice

What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively assuming the estimates were made at the 99% plus level?


A) .444
B) .667
C) 1.212
D) 1.469
E) 1.540

Correct Answer:

verifed

Verified

Related Questions

Q1: With scum, a prerequisite to being able

Q3: A big advantage of AON networks is

Q4: Milestones are not depended upon the predecessor

Q5: The actual project duration will be known

Q6: A diagram of nodes connected by directional

Q7: The critical path always has the largest

Q8: What assumptions are made about the probabilities

Q9: A task or set of tasks required

Q10: Which type of precedence diagramming convention is

Q28: What is a Gantt chart?

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines