Multiple Choice
A task is expected to take 20 hours of labor at $25 per hour. The required material cost is $500 and the organization charges 30% of direct labor for overhead. The total task cost is:
A) $500
B) $1,150
C) $1,250
D) $1,300
E) $1,500
Correct Answer:

Verified
Correct Answer:
Verified