Multiple Choice
There are three basic causes for change in projects and their budgets and/or schedules. Which of the following is not one of these?
A) Errors the cost estimator made about how to achieve the tasks identified in the project plan.
B) Inflation causes significant changes to the cost of labor and/or materials.
C) The project team or client learns more about the nature of the scope of the project or the setting in which it is to be used.
D) A new law is passed, a trade association sets a new standard, a governmental regulatory agency adopts a new policy.
Correct Answer:

Verified
Correct Answer:
Verified
Q59: Top-down budgeting typically results in better acceptance
Q60: Direct resource costs such as for materials
Q61: With top-down budgeting, overlooking a small but
Q62: A task is expected to take 20
Q63: Sean, a project manager, has to prepare
Q64: The project manager recognizes an expense when
Q65: Contrast between activity budgeting and program budgeting.
Q67: Activity budgets show expenses by task and
Q68: Individual elements of project budgets are generally
Q69: The first unit requires 10 hours to