Multiple Choice
Marcus is asked by higher management to create a document that provides a high-level description of a project that has not yet been approved. The document should describe the major deliverables of the project and should provide the financial and strategic justification for the project. In this scenario, Marcus needs to prepare a _____.
A) project baseline
B) RACI matrix
C) work breakdown structure
D) project charter
E) contingency plan