Multiple Choice
This is held on the first day of the sprint to determine the goal(s) for the sprint and to choose the product requirements from the product backlog that are aligned with the sprint goal.
A) Sprint planning meeting
B) Daily scrum
C) Sprint review
D) Sprint retrospective
E) Sprint collaboration
Correct Answer:

Verified
Correct Answer:
Verified