Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D) . The times required in minutes for each product on each machine are shown below: If management wishes to assign products to machines so that the total time to complete all the products is minimized, then Product 3 is assigned to
A) machine A.
B) machine B.
C) machine C.
D) machine D.