Multiple Choice
Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D) . The times required in minutes for each product on each machine are shown below: If management assigns products to machines so that the total time to complete all jobs is minimized, then the time to complete Product 1 is
A) 10 minutes.
B) 9 minutes.
C) 16 minutes.
D) 12 minutes
Correct Answer:

Verified
Correct Answer: