    A Job Has an 80 Percent Learning Curve
Solved

A Job Has an 80 Percent Learning Curve

Question 178

Question 178

Multiple Choice

A job has an 80 percent learning curve. The second unit required 12 hours to complete. Approximately how many hours will be devoted to the first five units (including those already completed) ?


A) 26
B) 36
C) 46
D) 56
E) 66

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q173: A firm is preparing a bid on

Q174: A simo chart includes:<br>A)delay.<br>B)storage.<br>C)transportation.<br>D)left/right hand movements.<br>E)inspection.

Q175: The manager of Lawn and Garden Services

Q176: Methods analysis and motion study techniques develop

Q177: A methods and measurements analyst needs to

Q179: A job had an observed time of

Q180: A methods and measurements analyst for Digital

Q181: The motion study chart that describes the

Q182: Which of the following is the formula

Q183: Which of the following is not considered

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines