A firm is preparing a bid on a city service contract for 80 shifts of a cleaning service. The operations manager estimates the time required for the first two shifts to be 17.8 hours and 15.1 hours respectively. What is the appropriate learning curve?


A) 75 percent
B) 80 percent
C) 85 percent
D) 90 percent
E) 95 percent