Multiple Choice
A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:
What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of job time is used?
A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q94: In a stopwatch time study, the average
Q95: Process chart symbols do not include:<br>A)delay.<br>B)inspection.<br>C)operation.<br>D)rejection.<br>E)storage.
Q96: A methods and measurement analyst wants to
Q97: From the worker's perspective, an output-based pay
Q98: Which is not a requirement for an
Q100: An 80 percent learning curve means that
Q101: Methods analysis is more likely to lead
Q102: The manager of Lawn and Garden Services
Q103: Motivation influences quality and productivity, but not
Q104: In calculating standard times, allowance percentages normally