The Minimum Possible Cycle Time in a Typical Product Layout

Question 99

Multiple Choice

The minimum possible cycle time in a typical product layout with no parallel activities is determined by the


A) longest task time.
B) shortest task time.
C) average task time.
D) total task time.
E) per-unit setup time.

Correct Answer: