Multiple Choice
A production line is to be designed for a job with three tasks. The task times are 0.4 minutes, 1.2 minutes, and 0.5 minutes. The maximum cycle time in minutes is
A) 0.4.
B) 0.5.
C) 1.2.
D) 2.1.
E) 0.7.
Correct Answer:

Verified
Correct Answer:
Verified