Multiple Choice
Project management differs from management of more traditional activities mainly because of:
(I) its limited time frame.(II) its unique, defined set of activities.(III) the requirement for use of the appropriate resources.(IV) the need for planning and execution.
A) I
B) II
C) I and II
D) I and III
E) I, II, and IV
Correct Answer:

Verified
Correct Answer:
Verified
Q71: The earliest finish time for an activity
Q72: Which of the following is not typically
Q73: To _ an activity means to shorten
Q74: The project management strategy of injecting additional
Q75: The sum of times of the longest
Q77: An advantage of Gantt charts in project
Q78: The advantage a precedence diagram has over
Q79: The costs associated with risk events tend
Q80: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q81: If two consecutive activities on the same