menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Statistics
  3. Study Set
    Operations Management Study Set 5
  4. Exam
    Exam 17: Project Management
  5. Question
    Consider the Following Work Breakdown Structure
Solved

Consider the Following Work Breakdown Structure

Question 80

Question 80

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? A) 160 days B) 170 days C) 200 days D) 210 days E) 300 days
What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q75: The sum of times of the longest

Q76: Project management differs from management of more

Q77: An advantage of Gantt charts in project

Q78: The advantage a precedence diagram has over

Q79: The costs associated with risk events tend

Q81: If two consecutive activities on the same

Q82: When developing probabilistic estimates of project duration,

Q83: Some organizations use a matrix organization to

Q84: Which of the following is not true

Q85: Which of the following leads to simulation

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines