Multiple Choice
Consider the following work breakdown structure:
What is the estimated expected (mean) time for project completion?
A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q75: The sum of times of the longest
Q76: Project management differs from management of more
Q77: An advantage of Gantt charts in project
Q78: The advantage a precedence diagram has over
Q79: The costs associated with risk events tend
Q81: If two consecutive activities on the same
Q82: When developing probabilistic estimates of project duration,
Q83: Some organizations use a matrix organization to
Q84: Which of the following is not true
Q85: Which of the following leads to simulation