Multiple Choice
Which of the following is not a form of risk reduction in project management?
A) backup system
B) outsourcing
C) risk sharing
D) scenario analysis
E) frequent monitoring of critical project dimensions in order to catch and eliminate problems early
Correct Answer:

Verified
Correct Answer:
Verified