Multiple Choice
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is
A) 3.
B) 5.
C) 9.
D) 16.
E) 25.
Correct Answer:

Verified
Correct Answer:
Verified