Multiple Choice
A hierarchical listing of what must be done in a project is called a
A) work breakdown structure (WBS) .
B) PERT.
C) planning matrix.
D) crashing plan.
E) critical path.
Correct Answer:

Verified
Correct Answer:
Verified