Multiple Choice
Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately
A) 5.
B) 6.
C) 7.
D) 8.
E) 9.
Correct Answer:

Verified
Correct Answer:
Verified
Q100: The network diagram shows sequential relationships among
Q101: The standard deviation of the critical path
Q102: A hierarchical listing of what must be
Q103: Many activities have slack time; if we
Q104: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q106: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q107: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q108: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q109: Once a project is approved and underway,
Q110: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"