    Activity 4-5 in a Network Diagram Has an Optimistic Time
Solved

Activity 4-5 in a Network Diagram Has an Optimistic Time

Question 105

Question 105

Multiple Choice

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately


A) 5.
B) 6.
C) 7.
D) 8.
E) 9.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q100: The network diagram shows sequential relationships among

Q101: The standard deviation of the critical path

Q102: A hierarchical listing of what must be

Q103: Many activities have slack time; if we

Q104: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q106: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q107: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q108: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q109: Once a project is approved and underway,

Q110: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines