menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Statistics
  3. Study Set
    Operations Management Study Set 5
  4. Exam
    Exam 17: Project Management
  5. Question
    Consider the Following Work Breakdown Structure
Solved

Consider the Following Work Breakdown Structure

Question 108

Question 108

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated slack time for activity D? A) 0 days B) 19 days C) 20 days D) 79 days E) 80 days
What is the estimated slack time for activity D?


A) 0 days
B) 19 days
C) 20 days
D) 79 days
E) 80 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q103: Many activities have slack time; if we

Q104: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q105: Activity 4-5 in a network diagram has

Q106: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q107: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q109: Once a project is approved and underway,

Q110: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q111: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q112: A sequence of activities that leads from

Q113: In project network analysis, "slack" refers to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines