Multiple Choice
Consider the following work breakdown structure:
What is the probability that the critical path for this project will be completed within 52 weeks?
A) .1554
B) .3108
C) .3466
D) .6554
E) .8277
Correct Answer:

Verified
Correct Answer:
Verified