A Scheduling Rule Used for Sequencing Jobs Through Two Work

Question 38

Multiple Choice

A scheduling rule used for sequencing jobs through two work centers such that makespan is minimized is


A) critical ratio rule.
B) Johnson's rule.
C) slack per operation rule.
D) shortest processing time rule.
E) Pareto rule.

Correct Answer: