Multiple Choice
There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
After the row and column reductions, what is the minimum number of lines needed to cover all of the zeroes?
A) 0 lines
B) 1 line
C) 2 lines
D) 3 lines
E) 4 lines
Correct Answer:

Verified
Correct Answer:
Verified
Q34: There are four resources and four jobs
Q35: The EDD priority rule usually does well
Q36: Input/output (I/O)control refers to monitoring the productivity
Q37: Bottlenecks in service systems may shift with
Q38: A scheduling rule used for sequencing jobs
Q40: A work center can be a:<br>(I)machine.<br>(II)group of
Q41: A Gantt chart is a basic scheduling
Q42: Average completion (flow)time for a schedule sequence
Q43: Line balancing is a major factor in
Q44: The theory of constraints has a goal