Multiple Choice
In an assignment model where there are fewer jobs than resources
A) dummy jobs are needed to solve the problem.
B) dummy resources are needed to solve the problem.
C) the problem cannot be solved using an assignment model.
D) the problem will have multiple optimum solutions.
E) the simplex method must be used to solve the problem.
Correct Answer:

Verified
Correct Answer:
Verified