Multiple Choice
The following table contains information about five jobs waiting to be processed at work center number three.
The sequence that would result using the SPT rule is
A) e-b-c-d-a.
B) c-a-b-e-d.
C) a-d-c-e-b.
D) d-e-b-a-c.
E) e-d-b-a-c.
Correct Answer:

Verified
Correct Answer:
Verified