Multiple Choice
The MRP input storing information on the status of each item by time period (e.g., scheduled receipts, lead time, lot size) is the
A) master production schedule.
B) bill of materials.
C) inventory records.
D) assembly time chart.
E) net requirements chart.
Correct Answer:

Verified
Correct Answer:
Verified