In MRP, the Gross Requirements of a Given Component Part

Question 82

Multiple Choice

In MRP, the gross requirements of a given component part are calculated directly from


A) net requirements + projected on-hand inventory.
B) gross requirements of the immediate parent.
C) planned order releases of the end item.
D) net requirements of the end item.
E) planned order releases of the immediate parent.

Correct Answer: