Multiple Choice
Demand calculations for sizing of the alternate power source(s) for a hospital shall be based on any of the following: (1) prudent demand factors and historical data, (2) ____, (3) Article 220 feeder calculation procedures, or (4) any combination of the preceding.
A) average load
B) peak load
C) connected load
D) cable (material) capacity