The is the product of the percentage completed and the sum of the estimated costs of all the specific activities that make up a work package or the project.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)
Correct Answer:

Verified
Correct Answer:
Verified