Multiple Choice
The cost performance index (CPI) is a measure of the cost efficiency with which the project is being performed.If the cumulative earned value is greater than the cumulative actual costs, then
A) the CPI is greater than 1.0.
B) the CPI is less than 1.0.
C) CPI cannot be determined with CEV and CAC.
D) the CPI is negative.
Correct Answer:

Verified
Correct Answer:
Verified
Q87: It is good practice to have the
Q88: It may be easier to estimate the
Q89: Committed costs need to be treated in
Q90: Determining the earned value involves collecting data
Q91: As data are collected on _, including
Q93: In many cases, there will be a
Q94: The first method for determining _ assumes
Q95: Cumulative actual cost (CAC)should be calculated to
Q96: Calculate the forecasted cost at completion if
Q97: It is important to use the _