Multiple Choice
If the cumulative earned value is R10 and the cumulative actual costs are R20, then the CPI is
A) R10.
B) -R10.
C) 0.5.
D) 2.0.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q33: At the beginning of the project, it
Q34: The is the amount that was budgeted
Q35: Facilities costs in the project costs estimate
Q36: Determining the earned value involves collecting data
Q38: Consider a project that involves painting five
Q39: Which of the following is not a
Q42: Labour costs in the project costs estimate
Q64: When the CPI goes below 1.0 or
Q91: As data are collected on _, including
Q93: In many cases, there will be a