Multiple Choice
Which of the following is not a way to reduce the costs of activities:
A) Reduce the scope or requirements
B) Substitute less expensive materials.
C) Assign a person with less expertise or less experience to perform or help with the activity.
D) Increase productivity through improved methods or technology.