Multiple Choice
Calculate the forecasted cost at completion if the total budgeted cost is R150 000, the cumulative actual cost is R100 000, and the cumulative earned value is R120 000.
A) FCAC = R70 000
B) FCAC = R170 000
C) FCAC = R130 000
D) FCAC = R370 000
Correct Answer:

Verified
Correct Answer:
Verified