Multiple Choice
Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - estimated duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES • estimated duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + estimated duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + estimated duration.
Correct Answer:

Verified
Correct Answer:
Verified
Q11: The development team develops, delivers, and demonstrates
Q33: The project control process involves all of
Q50: The latest finish time for a specific
Q61: A consistent time base, such as hours
Q73: If the planned corrective actions do not
Q83: Calculate the earliest start for Task D
Q100: Earliest start time (ES)is the earliest time
Q102: The amount of slack should determine the
Q104: For large projects that involve several hundred
Q126: The earliest start time for a specific