Solved

Earliest Finish Time (EF) Is the Earliest Time by Which

Question 75

Multiple Choice

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated


A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - estimated duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES • estimated duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + estimated duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + estimated duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions