Multiple Choice
Each activity in a network diagram is represented by a box in the , and the of the activity is written within the box.
A) work breakdown structure; name
B) network diagram; description
C) project scope document; responsible organisation
D) responsibility assignment matrix; name of the responsible person
Correct Answer:

Verified
Correct Answer:
Verified