____ are the products or outputs that the project team or contractor will produce and provide to the customer during and at the completion of the performance of the project.
A) Contracts
B) Acceptance criteria
C) Deliverables
D) Responsibilities
Correct Answer:

Verified
Correct Answer:
Verified