Solved

On 1 January 2017, Peter Ltd Signed a Contract Worth

Question 15

Multiple Choice

On 1 January 2017, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows: On 1 January 2017, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:   Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2017, 75 per cent complete at the end of 2018 and 100 per cent complete at the end of 2019. Revenues and costs were as estimated. How much profit was earned during 2019 if the percentage of completion method was used? A)  $3 500 000 B)  $5 600 000 C)  $14 000 000 D)  None of the above Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2017, 75 per cent complete at the end of 2018 and 100 per cent complete at the end of 2019. Revenues and costs were as estimated. How much profit was earned during 2019 if the percentage of completion method was used?


A) $3 500 000
B) $5 600 000
C) $14 000 000
D) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions