Multiple Choice
On 1 January 2017, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows: Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2017, 75 per cent complete at the end of 2018 and 100 per cent complete at the end of 2019. Revenues and costs were as estimated. How much profit was earned during 2019 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $14 000 000
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q10: Junction Company had the following transactions, among
Q11: Leslie Ltd has found an error in
Q12: With respect to services provided, it is
Q13: On 1 January 2016, Romulus Ltd signed
Q14: The income statement of Berrima Barbed Wire
Q16: The percentage of completion profit for a
Q17: Opec Ltd manufactures crystal balls. Transactions for
Q18: Highrise Constructions Ltd had a large three-year
Q19: Although revenue may be recognised at various
Q20: Revenue should be recognised when: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8763/.jpg"