Multiple Choice
According to Ohno and Toyota, _____ is a category of waste that retains unnecessary inventory between process steps.
A) excess inventory
B) overproduction
C) over-processing
D) waiting time
E) None of these answers.
Correct Answer:

Verified
Correct Answer:
Verified